[問題] Risk 的問題
看板P_Management (專案/產品管理)作者LadySara (莎拉夫人)時間16年前 (2009/05/23 23:06)推噓1(1推 0噓 2→)留言3則, 2人參與討論串1/3 (看更多)
Which of the following is the MOST likely cause of poor risk management ?
A: Inadequate risk response planning.
B: Poor risk monitoring and control.
C: Lack of a prioritized list of risks.
D: Lack of detail in the scope statement.
There is a probability of 0.10 that a given risk will occur in a project.
If it occurs, it will result in a loss of US $10000.
The insurance cost for this event is US $700,
with a deductible amount of US $250.
Should a rational project manager buy this insurance ?
A: Yes, since US $1000 is greater than US $950.
B: Yes, since US $1000 is greater than US $700.
C: No, since the deductible amount changes the expected value of the risk
event.
D: No, since US $1250 is greater than US $ 1000.
這題答案跟我選的不一樣,但我腦筋轉不出來....
一整個不明白為什麼.....
--
※ 發信站: 批踢踢實業坊(ptt.cc)
◆ From: 123.194.171.53
→
05/24 00:46, , 1F
05/24 00:46, 1F
推
05/24 09:01, , 2F
05/24 09:01, 2F
→
05/24 09:01, , 3F
05/24 09:01, 3F
討論串 (同標題文章)
完整討論串 (本文為第 1 之 3 篇):
1
3
P_Management 近期熱門文章
PTT職涯區 即時熱門文章
15
37